General update

Yesterday we did our PCI inspection.  I was writing a PCI post and added this general update about what has changed, but the post was getting a bit unweildy, so I have split the two.  The PCI post is here.

Since the last time we were inside the house was a few weeks ago, we saw a few new things while we were there.  Of course, defects not withstanding, the house is now "complete" so most outstanding matters have been attended to.  I didn't take any pictures yesterday, so probably won't have any picture updates until handover.

Kitchen


I saw for the first time (and Robert for the first time not through a window) the kitchen splashback, and the lights under the overhead cabinets in the kitchen.  With those lights on the splashback looks decidedly grey (as opposed to the brownish tone that it actually is) which I think is a bit of shame, but Robert tells me only I can see a difference.  Besides, it's not like it looks terrible.

Bathrooms


The missing tile in the bathroom has been replaced, and the bath has been fixed in position.  The shower drain "grilles" have also been fitted (they're not really grilles though, I just don't know what they're called).

Roof


The part of the roof that needed repairing has been repaired.

Front Door (and a little about the bi-folds)


The front door has been painted; apparently the painter was only in yesterday morning and the paint was still a bit wet, which is why there was still paint on the glass that will be cleaned.  Apparently the painter was cringing as he painted our beautiful door; paint over stain is not a popular option for this range.  I'm not sure if I've explained it before, but I'll take a minute here to talk about it here.

The look we have gone for in the house is reasonably modern, but neutral.  Our last house had a lot of timber features and while it looked great for the most part, maintenance was an issue.  We were therefore happy enough that aluminium windows and external sliding doors were standard, and decided to go with aluminium bifold doors as well.  The doors would match our windows, and also the sliding door from the rumpus room to the alfresco (if we had gone timber then I would have wanted that door to match so we would have had to upgrade that door).  We like the bifolds not so much for the look, but for the effect they have when open, so for that reason we didn't mind that the aluminium doors, on their own, don't necessarily look as good as timber.  The consistency through the house and the reduced maintenance was benefit enough for us.  We certainly got the impression at the office that it was an uncommon choice, and our Site Supervisor yesterday commented that he had never done a house with aluminium bifolds before.

So, when it came to the front door, it was looking like being the only timber feature of the house.  It is a beautiful door, but as with the bifolds it wasn't going to suit the house or our tastes.  Moreover, much of the striking-ness (??) of this door is in its size, which it doesn't lose by being painted.  We decided to paint the door, and it is still a wonderful, grand feature.

Preparation for after handover


The company we are using for our blinds have confirmed that our blinds are currently being made and should be ready this week; hopefully we can arrange installation as soon as possible after we are in.  We have bought our lights for the front pillars, and have decided on a feature pendant for the bedroom.  We still need to decide on light fittings for the rest of the rooms that don't have down lights.

Wednesday, 10 October 2012

Standing on the outstide, looking in...

Yesterday evening Robert went to check out the house, hoping to see that some painting had been done.  According to the site supervisor, the painters were supposed to come last week (while he was on leave) to do the external painting, but they hadn't shown up.  When he returned from leave on Monday and found out he organised for them to come on Tuesday.

Usually I'm wielding a camera, but all Robert had with him was his phone.  He was in a hurry and we're still locked out, so hopefully the photos below show the progress adequately.


Paint


As hoped, the painters had been and done most of the external painting.  The front door hasn't been painted yet, but otherwise it appears to all be done (although not without faults).

Painting
Paint - Render, Cladding & Eaves
Paint - Eaves
Paint - Alfresco Roof and Beams

 

Doors


The front door handle has been fitted, as well as the metal strip above the bifolds, so they meet the dricks (or at least it looks like they do).  The final door, the rear garage door, has also been painted and hung.

Door handle
Bifolds
Rear garage door

 

Inside


There's not much we know about inside.  We can see that the splashback has been installed, and the lights under the overhead cabinets in the kitchen (which were presumably waiting for the splashback) have been fitted.

Kitchen (through the bifolds)

Meter Box


The meter box has been changed from the ugly building one.  I wasn't there, so I can't be sure it isn't a trick of the light in the photo, but I think it is the wrong colour.  It should be Colourbon Jasper (same as the down pipes) but it looks to me like Woodland Gray (same as the roof and garage door).

Meter Box

PCI is booked in for Monday afternoon, which just happens to be mine and Robert's birthday. Everything is crossed for a handover late next week!

Monday, 8 October 2012

Nothing to see here (updated 5 hours later)

The title pretty much says it all!  For the first time since construction started, we didn't visit the block this weekend.  Robert was out there late last week to get a second quote on the alfresco screens, and found that for the first time, the house was completely locked up.  I guess it had to happen eventually!

However Robert was able to see a couple of changes.  Most notably, the splashback has been installed and all the windows and doors have flyscreens, with the exception of the bifolds and the front door.  The bifolds won't have a screen (they don't come under the BAL definition requiring one) but the front door is supposed to have one.  Although in truth, we don't care if they don't put one on the front door!

While we don't know what is left to do inside, we do know that (as of Thursday) the external painting is yet to be started.  Such a shame given the beautiful weather last week and the forecast rain for this week.

The tiles have been cleaned, presumably in preparation for PCI, which is scheduled for this Wednesday.  We are having some troubles booking our independent inspector, but hopefully we are able to sort that out and go ahead this week!

UPDATE 2pm


Robert has spoken to our site supervisor, who says that the house won't be ready for PCI on Wednesday.  A shame, but it does mean that we can go ahead with our usual inspector on Monday.

The supervisor also mentioned that the front door is going to be replaced with a fire-resistent version (we noticed a 'spare' door had been delivered a few weeks ago, but figured it was a mistake).  This means that we don't have to have an ugly flyscreen door covering our feature entrance door!  It's a great win for us!